Wednesday, July 7, 2010

July 4th weekend

Arrived at Stony on Thursday night and stayed in the John Dwyer camp. The Joe Dwyers were up (32 of the 46?), as was Joe Stevens, and it was such a pleasure to have such friendly, gracious company for the weekend. Wish I could remember all the kids names but names were never my strength.

Tim and Nick installed the 16' beam on Thursday, using 2x's to shim up each end 1.5" at a time. Tim thinks it weighs 600 lbs. LoknLogs does not skimp on structure. This is built to last. Got a delivery of materials from Widmeyer on Friday (mostly porch boards) and helped Tim and Nick finish setting floor joists and the 8' beam for the second floor. Joe Dwyer helped me put in half the porch boards on Saturday, while Cory sorted and lugged logs up to the camp (hurting his back). Gerry came by on Sunday and we finished the porch. We put down screen under the boards to discourage bugs from attacking us from the below.

Unbelievable fireworks party across the lake on the 4th I am told, but I was so exhausted, I went to bed at 9PM and actually slept thru it with the help of some ear plugs. Over the weekend, Paula, Cory and I sorted the rest of the logs and brought them up from the driveway so they are now stacked inside in the order we need to access them for every course. Mind you they go up in the air now, so need to get some scaffolding for the south gable end.

Cory and I attacked the dormer on the lake side, and got about half the courses up before we had to leave. Tim and Nick got the porch headers up Tuesday and were starting back on the cabin for a day or so. Paula walked around and took some snaps with my Blackberry to show where we are.

Sunday, June 20, 2010

Top of the windows

Notes on the site as of last Tuesday. Nick and Tim (and I) did get the logs over the windows on Wednesday, but that is not shown at this point. Getting logs over the windows to line up takes a bit of effort with braces and come-alongs.


reposted this with better video, as I finally figure out my avhcd to youtube settings

Iron Worker Weekend

Joe, Marty, Anne, Tess, PJ and Riley all came up and pitched in over the weekend.   Joe and Marty made the door/window frames and figured out bracing, while PJ figured out how to set a control line for use with the PLS 5 square laser to check that walls are vertical (not leaning). They are a hard working team.

Lok-N-Log Training Day

Day 1 is delivery, and day 2 is training.   Lok-N-Log's Barry Campbell came up from Sherburne and patiently explained how to put the kit together.   Here are some clips for the record.   


Part 1 of 3


Part 2 of 3


Part 3 of 3

Saturday, June 19, 2010

Logs arrive

Lok N Logs dropped off 2 tractor trailers full of logs at the snow plow turnaround on Thursday the 10th. From that point, the dirt road is so narrow and twisty that you need a smaller truck. First truck was a commercial carrier and showed up at 9:30A, although I had been promised an 8A delivery time over and over. Right. Or maybe 9:30??

We used a JCB rough terrain forklift to unload the trucks and load up 3 trailers. At the site, a Lull (similar to the JCB) unloaded the trailers and carried pallets up the driveway. Once there, they got unloaded and the first 20 courses (rows from the bottom) got sorted. Each log is numbered and labeled, so easy to tell exactly where it goes in the wall.

Logs have a tongue on top and a groove on the bottom so they interlock. The tongue gets a foam gasket, and caulk at the edge, and then 9" log hog screws hold the logs in place. Seems very solid and very tight. Caulk oozes out here and there, and some cleanup is needed. Barry Campbell of LokNLogs came out Friday and led a training session. Tim Lee, Nick, Luke Waite and I got about 4 courses down. On Friday night, cousins Marty, Joe and Anne came up with a friend, Tess. Saturday was a bit rainy, but Marty and Joe made window and door frames and then we set them in place. The walls at the porch door were way out of level vertically, so we used a come-along and some braces to fix that. PJ and son Riley joined us on Sunday and we leveled the rest and set the frames in place along with a couple more courses.

M/T/W it was off to the races laying logs with all the braced frames keeping them honest. We lowered two small windows a few courses, as they were ridiculously high in the air. The designer lined up the heads with big windows which made no sense, and I did not catch the error till Monday. Tim and Nick figured out how to swap some rows so it still worked out.

Friday, May 28, 2010

Framing -May 2010

Fabulous weather and lots of help, so we got the framing done.   Ger, Bren and I checked level and square with my laser tool, and then we got posts, sills, rim joists up,  then Luke Waite helped us set beams and joists, and then they went back to the real world, and I stuck around a few more days with Tim Lee and Nick to finish.  

Here is a short clip showing where we are now.  

Sunday, April 25, 2010

April Summary

Went up north last weekend and with help got the site prepped for the foundation.   Met with power company and contractors. Foundation work is underway and should be finished up in a week or so.  

Rained and snowed, but here is a short clip of the site from the day I left it.  Got a nice Canon video camera now, so you might not get nauseous trying to watch  this one.


Sunday, April 11, 2010

Pump Monster

I bought a portable pump at the local HD last fall to pump water up into the stock tank and run the pressure washer and make concrete.   It came with 1" threaded fittings and an adapter for garden hose.   Since I need to pump about 200 feet and 50 feet vertically, garden hose is pretty feeble.  So, I bought some 1" flexible pipe... but turns out the pump is Italian and has British Standard Pipe threads which are bloody useless in the States.   So I had to use the garden hose adapter and a pile of fittings:
  • 1" BSP to garden hose
  • garden hose to 3/4 NPT 
  • 3/4 NPT to 3/4 pipe
  • 3/4 pipe to 1" reducer bushing
  • 1" bushing to 1" coupling 
  • coupling to black pipe 
Looks ridiculous, but .... this took me awhile to figure out so it looks good to me. 

Now all I need is expansion tank, pressure switch and a pumphouse.  


Saturday, April 10, 2010

Opening the site

First trip for 2010 next weekend. Heading up Thursday night to meet National Grid on Friday, as well as contractor(s) too about foundation and shell. Other tasks for this trip in order of importance:

  • Set up strings over the perimeter showing where foundation wall gets placed.
  • Set strings for porch and center line piers
  • Drill holes for rebar 
  • Chisel rock to 3 in 12
  • Build forms for footers using scribed plywood 
  • Build 2x4 staging platforms for logs 

Thursday, February 18, 2010

Foundation

Asked structural engineer to do another plan, this time with concrete block foundation and alternate for poured foundation. Motivation was pricing of micro-lams needed for the pier type foundation, worry about lugging them microlams into place, and a solid wall is better for snow anyway. Cost is probably equal, but we will never REALLY know.

Insanely frantic at work, partly on software, web, marketing type projects (infrastructure for knowledge based biz), so hard to focus.

Monday, December 7, 2009

National Grid

National Grid called (at 7PM!) and said "You need to get easements from your neighbors plus copies of deeds plus copies of tax maps. If you can not get easements, you will not get power." I am half-hoping we don't get it, since I have some goofball ideas about 12V power and PV panels that I might get to try, although realistically the budget is long gone already.

I met neighbor Harry Ostrander the other week (other side of Thisse camp) and he wants power too and he is out next to Terry Thisse. If NG (did no one in marketing notice the initials?) brings power to more than one person, the 7.6 kV primary line is free, residents just pay for the secondary line. So I need to call all these people and chase things down, and see what happens.

Wednesday, December 2, 2009

Notes from Thanksgiving Work (2/2)

The "after pictures" of the bedrock are shown here, plus I wander down by the lake mumbling about the dock.

Thanksgiving work - Dirt

Did not get very far on my do list when I realized that item 2 should be "dig out bedrock completely." Stayed with Tim and Cathy Buckingham in town who let me take showers and fed me as well (very nice!). Despite wearing the natty rain pants shown in the video to keep mud off my pants, I brought quite a bit of that mud into their house. This short video just shows me doing work (drill hole and dig), so not terribly interesting, but gives you an idea of what I did for 3 or 4 days.

Thursday, November 26, 2009

Plans

Latest set of plans are in the documents section of the web site.


Saturday, November 21, 2009

Packing


It takes awhile to get all loaded up, and I live in terror I will arrive having left something important 400 miles due south. Darn near forgot my rotary hammer and that would have been very, very bad. Hoping snow does not stop me (note the one non-Virginia tool in the pile), and likely staying in Lowville this time at the invitation of Tim Buckingham, or TimBuck2 as Gerry says. Do list this time might be:

1) Drill holes in rock (with rotary hammer) for batter boards
2) Set Batter boards and cross pieces
3) Set string and layout foundation - square it up
4) Use pressure washer to clear dirt from area of 24" diameter foundation piers.
5) Measure spot for each pier per structural plans
6) Use drill and chisels to level rock in area of each pier per structural plan (max slope of 3 in 12).

Might see if I can pick up my green lumber from the O'Brien sawmill made from our trees. Needs to be stacked up and covered with a tarp. And there is always more clearing to do, this time down towards the lake.

Monday, November 16, 2009

Batter boards - 4 per corner

Made batter boards Sunday from 2x4's and rebar. Cut 24" rebar into 8" pieces, drilled 5" deep holes (1/2" round) into ends of 2x4's and then hammered the rebar into the 2x4's. On site, I will drill 4" deep holes in bedrock and drop rebar'd boards into hole.

Not very straight despite actually trying to be straight, but in theory that is ok since I will use builder's level to identify point to level the crosspiece and attach string. Think I will use the 4 boards per corner pattern (see image from www.cedarshed.com below), not the 3 board pattern shown in a prior post.

Saturday, November 14, 2009

Adirondack Lake Survey

Anyone know if lake pH is checked regularly by a scientists (not that I don't trust my pool strips - guess I could try those!)? I found a 1986 survey of fish, shoreline, geography, etc: http://www.adirondacklakessurvey.org/alscrpt.php?alscpond=040617. Chasing links, I see USGS has some 1955 photos from 12,000 feet, but quality is about the same as they used for bombing German factories ten years prior to that, so hard to read any details.

Thursday, November 12, 2009

Logs into boards

The logs we cut and trimmed are scheduled to be piled into Bill Lee's trailer tomorrow by Tim Buckingham. From there, they head to Bill O'Brien's sawmill near Port Leyden to be cut into 1" rough sawn boards, which need to be stacked back here on site and covered with a tarp so they dry out slowly over the next year. Tim B is on site this week ripping out stumps and digging out dirt at foundation and a few other heavy duty tasks that require a skid steer.

Not sure what the boards are for, but maybe a pump house, or a shed, or a little camp, or a platform, or fencing, or closing in the crawl space, or steps to the lake. They need to be primed and stained to last outside of course, or sanded to be useful as shelving or paneling inside.

Batter boards


Hope to set batter boards at my next visit. This image from shedsusa.com gives you some idea of what they look like. Batter boards are needed to square up the foundation, yielding a rectangle instead of the dreaded parallelogram. Of course, our land is not flat, and this technique will not work unless the strings are horizontal, so I got a builder's level to set string height accurately.

And (of course) we have no dirt to hold up the vertical batter boards, just rock. So, I am drilling a 4" deep hole in the bottom of the 2x4 batter boards with a 1/2" drill bit and pounding an 8" rebar into the 2x4. On site, I will drill a 5" deep hole into rock for each vertical board and drop the rebar'ed 2x4 into the hole. Nothing to it. I hope.

Saturday, November 7, 2009

Big rocks

Evan suggested that if these are going to be moved with a skid steer, that perhaps they could be moved to become an entrance feature.

From Halloween 09 at Stony
E: "I love the boulders! they are not easy to move, but you are talking about that...and I wondered what it would be like to have a few of them as part of the way into the cabin, perhaps forming the base for the entry platform, or, with that big one you can't get going to the lake...it might be high enough to form part of the base to the DR doors..or even have the deck post come down on it.. some of the flatter ones could be part (a landing) of the walk up to the cabin from the pkg lot ....I also liked the tree close to the house....it is amazing when trees and boulders are a part of the way the cabin hits the ground because they give an immediate sense of authority, of place, like the cabin has been there awhile......so finding ways for the boulders to be integrated into the site, into the walks and decks and maybe holding up dirt here and there where it is needed."