Planning for 19th-24th

Before arrival
  1. Get building permit if possible from Paul Gyore (sealed roof plan needed now, or later?)
  2. Discuss concrete pour with supplier – hose reach ok? Driveway? Wed ok?
  3. Get 24” long #4 rebars – 30 or so.
  4. Get 16(?) 48” sonotubes (or 8 at 8’ or whatever HD has) in 12” round.
  5. Make 16(?) brace boxes for the sonotubes out of 2x4 (12x12 inside clear box, and a couple of legs that can be pinned to ground (rock?)
  6. Tools and materials - load up minivan. Add storage to rear and roof as needed.
On site
  1. Cut trees that need to come down in future and might be somewhere near the camp.
  2. Cut trees in future septic location, as we don’t want to cut a tree AFTER the camp is up if we can help it.
  3. Mark north property line setback (12’6”?)
  4. Layout camp footprint in soil approximately to match latest site plan
  5. Remove stumps in camp footprint area using skid steer – remove soil there?
  6. Scrape driveway with skid steer - add gravel or concrete to holes? IF SO, NEED GRAVEL DELIVERY AND PLACE TO PUT GRAVEL NEAR ROAD – CLEAR OUT DELIVERY ZONE WITH SKID STEER
  7. Set up batter boards (may need to anchor to rock?) and using builder’s level, set mason string to height of sonotubes
  8. Mark pier locations – dig out dirt there and cut sonotube height to fit.
  9. Drill rebar hole, epoxy rebar in place (1 per sonotube, except if slope spot – then a couple).
  10. Set sonotubes in place, and anchor wooden braces for each tube so they don’t move around.
  11. Snap chalk lines to show center points for each tube.
  12. At end of pour for each tube, bury a 6” SS ¼”x20 bolt upright with 3” showing to anchor sill plate.