Before arrival
- Get building permit if possible from Paul Gyore (sealed roof plan needed now, or later?)
- Discuss concrete pour with supplier – hose reach ok? Driveway? Wed ok?
- Get 24” long #4 rebars – 30 or so.
- Get 16(?) 48” sonotubes (or 8 at 8’ or whatever HD has) in 12” round.
- Make 16(?) brace boxes for the sonotubes out of 2x4 (12x12 inside clear box, and a couple of legs that can be pinned to ground (rock?)
- Tools and materials - load up minivan. Add storage to rear and roof as needed.
- Cut trees that need to come down in future and might be somewhere near the camp.
- Cut trees in future septic location, as we don’t want to cut a tree AFTER the camp is up if we can help it.
- Mark north property line setback (12’6”?)
- Layout camp footprint in soil approximately to match latest site plan
- Remove stumps in camp footprint area using skid steer – remove soil there?
- Scrape driveway with skid steer - add gravel or concrete to holes? IF SO, NEED GRAVEL DELIVERY AND PLACE TO PUT GRAVEL NEAR ROAD – CLEAR OUT DELIVERY ZONE WITH SKID STEER
- Set up batter boards (may need to anchor to rock?) and using builder’s level, set mason string to height of sonotubes
- Mark pier locations – dig out dirt there and cut sonotube height to fit.
- Drill rebar hole, epoxy rebar in place (1 per sonotube, except if slope spot – then a couple).
- Set sonotubes in place, and anchor wooden braces for each tube so they don’t move around.
- Snap chalk lines to show center points for each tube.
- At end of pour for each tube, bury a 6” SS ¼”x20 bolt upright with 3” showing to anchor sill plate.