CLEARING (still)
- drop the 75 foot dead pine at the top of the driveway
- burn brush that is frigging everywhere
- cut up all the downed trees into moveable sizes and stack nearby out of the way
- move huge stack of firewood on north side to be out of the way
- remove logs and brush at edge of driveway - false sense of flat area is probably unsafe
LAYOUT
- measure distance in front of camp - 10 feet plus
- re-orient camp in general and flag location including south entry deck
- square up camp - corners - 34x36, so 49.5' on diagonal
- set batter boards and string
- locate piers with marking paint
- dig out piers - wash out with pressure washer?
ROTARY HAMMER
- drill rock in pier locations
- chip out rock if necessary to flatten pier spot
OTHER
- test driveway if rocks laid, or meet someone willing to do driveway